Tag Archives: track

New Staging Yard tracks

Over the last week, a team at Barrowmore, led by Richard and comprising Kevin Bays, Mike Rapson and Phil Sutton, set about laying some additional roads at one end of the staging yard. The first project was to add three terminating sidings off yard track East 1. These are long enough to hold a full length coal train and, with East 1 used as a clear through track, will allow for trains to be backed in and pulled out as required – essentially adding three tracks to the eastbound staging. The new switches were connected to Digikeijs boards.

Later in the week, a decision was taken to lengthen two westbound tracks on the outside of the yard. Richard and Kevin lengthened yard track West 17 all the way round to just before the scenic section and track West 16  through to join slightly earlier. Whilst not adding extra tracks, the extra space available with multiple occupancy on each track is equivalent to two extra tracks. The two terminating tracks for passenger trains were also repositioned as shown:

Dave Faulkner has subsequently programmed the changes into Big Bear.

The missing crossover

Back in December 2023 Richard found a video we hadn’t previously seen – the Big Little Railroad of 1948 and 9 minutes 20 seconds into it can clearly be seen a crossover going into the passenger road from the west.

We quickly agreed that this be built and Richard embarked on the process – as shown in the photos below.

The new crossover gives lots of additional operating possibilities.

track!

In the week before Christmas and New Year the turnouts and tracklaying were completed by Richard and Mike. Once down only 14 feet of original track remained!  The ‘dropper’ holes (new and old) were filled with tissue paperby Steve to prevent ballast loss and the whole was airbrushed black by Mike.

Gareth (shown) and Steve then painted the sides of the track a rusty brown – avoiding any switch blades. Finally Steve ballasted the track (with help from Gareth) using real sieved coal from his coal scuttle.

December progress

Running up to Christmas we have carried on at great pace to finish the trackwork and scenic work on Mauch Chunk.

Richard has carried on turnout building and, having finished 12 (?) turnouts – many in groups – is now relaying the track on the front to accomodate them. This has produced a pile of old turnouts which have served us well for many years but are not reliable enough for the new exhibition running. Mike is also lending a hand with tracklaying.

Mike has carried on with the smoothing of the roadways, which currently look very smooth – a bit of weathering will make them more realistic.

Gavin has built the new backscene boards using 3mm ply and braced them with 1inch x 1inch timber (not shown). He has also varnished and primed them for Steve to paint.

Steve has carried on with weathering the walls and rockface and then moved on to ballasting the RH end of the layout and adding the rocks on the river edge. Ground cover has also been added to the hillsides with Woodland Scenics coarse and fine scatter in several colours and blends, prior to re-adding the trees.

The late Chris Bennet’s bridge (the earlier girder bridge) has been extended using the same techniques and and pieces to extend over the extra tracks.

storming ahead!

Since my last post, we’ve been storming ahead with getting Mauch Chunk ready for the CMRA show in Stevenage on January 13/14th.

Mike has been getting stuck in with improving the scenery and has done some work on the statue of the unknown soldier, as well as starting to relay all the roadways and extend them onto the new boards.

Steve has been continuing to work on the walls – painting them – and is modifying the ‘river’ bridge extending it to cross the new, increased track witdth.

Richard has been measuring up and re-templotting much of the pointwork and is now building a full replacement set to ensure flawless running. Some or all of this will be relaid before CMRA depending on time available.

Gavin has started to build new backscenes to fit the new, extended scenic section, ready for Steve to paint in the early new year.

Peter, of Big Bear fame, has reworked the software for us to allow operation on 1024×768 screens which will allow us to use ex-‘Point of Sale’ touchscreens if time allows.

Building a Turnout

This series of photos shows Richard building the last turnout pair (for now) for the scenic section. The technique is age-old and starts with a template drawn in and then printed out from Templot to fit the space precisely.

Copperclad strips are first laid on sticky back tape on top of the template. The centre rails are then laid including the points of the crossing V. The next shot shows the gauges used: The NMRA HO gauge, and two OO rolling gauges. Outer rails are then added and then their opposite pairs. Next come the switch rails and then the frogs (with a caboose being run over by Richard to demonstrate clearance). Then the tie bar is carefully added with all clearances first checked for smooth opearation. Next the guard rails – which are pretty much cosmetic if eveything else has been done properly. This completes the turnout except only for gapping the conducting copperclad ties/sleepers.

A couple of shots show the Tortoise motors we are using with these new, hand-built turnouts – to reduce damage from the rapid throw of a Peco turnout motor – and the MERG board specific to Tortoise motors.

Final three shots show the turnout pair being laid on the ‘last’ scenic board at the LH end, and then in all the glory.

Destruction and Rebirth!

Well, that is a slightly grandiose title, but to an extent it does describe the work of the last ten days on the right hand of the scenic section!

We’ve taken up some of the old turnouts and cut back the track to a clean board finish. The board was then widened by just under three inches by Steve and Gavin to take an extra yard track. After careful levelling, cork was laid and then track and new turnouts, handbuilt by Richard, were carefully laid by Richard and Steve. The intention is to scenic the large, curved, end board at a later stage.

Wiring then commenced – these handbuilt turnouts will be powered by Tortoise point motors which give a more realistic movement and also reduce stress on the handbuilt soldering joints.

(Nearly) Finished Tracklaying!

Work has continued on laying the track and switches this month (March) and the track in the staging yard is now complete to the end points of the curves. Richard and I (Steve) have done most of this and Dave has corrected some of my worse errors! This is as far as we can go until the new boards on the front are complete – which will hopefully be in the next couple of weeks. The N&W caboose runs very happily through all the curves and switches although it will soon be recolored and decaled!

You can see that we have avoided using the double slips which proved a little problematic with some stock on the phase 2 staging yard boards.

We’ve now moved on to wiring.

Rapid track laying

Since returning from Model Rail Scotland and as we go into March incredible progress has been made laying track in the new staging yard. Richard and Steve have forged ahead with this as the photos show. Each piece of track has a duplicate pair of droppers soldered under the rail and copper strip is used at baseboard edges to hold the track firm there. Track is then glued down at each end of every fourth tie using cheap superglue. All track is Peco streamline code 75 and switches are now also being laid, initially by Richard.

Oh dear – I’m repeating myself in the excitement!

A quiet month (for Mauch Chunk PA)!

February was quiet for Mauch Chunk PA because we (BMRG) were getting Mostyn ready for Model Rail Scotland on 24-26th February and there is only room for one large layout to be erected in the clubrooms. Good news in that Mauch Chunk has now also been invited to MR Scotland in 2019!

As soon as we returned, Mostyn and Johnstown Road (the club’s O-gauge layout) were carefully stored in a large, linear pile along the rear side of the clubrooms and the new Mauch Chunk staging yard boards were re-erected and levelled.

Track laying has now started – using Peco streamline code 75 track. The Barromore MRG approach is being followed with droppers under the track and track held down with superglue. It is also VERY, VERY straight! Photos show Richard laying track although Steve (me) and Dave Faulkner are also involved.